As Lismore rebuilds after the flood, people are keen to know when, and if, the town's important infrastructure will reopen.
Create a free account to read this article
$0/
(min cost $0)
or signup to continue reading
![More than 100 Lismore City Council assets were impacted by the 2022 floods. More than 100 Lismore City Council assets were impacted by the 2022 floods.](/images/transform/v1/crop/frm/154120782/9898ff19-bf05-4c7e-8556-2f0a3203d317.png/r67_17_1015_684_w1200_h678_fmax.jpg)
While many are open now, or will open by the end of the year, some might take a little bit more time - but the good news is, they will be back.
Lismore council says 100 of its sites were affected by the February and March 2022 flooding events, including buildings, parks, public toilets and facilities.
As assessments continue, the council says the number of sites damaged by flood or storm water continues to grow.
MORE STORIES:
"The Scope of work required on each site is yet to be finalised. Therefore dates regarding the availability of council's buildings, parks and facilities are subject to change. Additionally, the availability of contractors and materials may cause delays in the progress of the restoration projects. Some restoration works are also subject to weather conditions which may cause delays," the council states.
Listed are seven community assets that will reopen next year and the estimated completion dates of the rebuild projects.
![Lismore Airport Terminal is expected to open in June 2023. Lismore Airport Terminal is expected to open in June 2023.](/images/transform/v1/crop/frm/154120782/ee969409-8c48-446e-81eb-afcf59aacb6d.jpg/r0_181_1772_1181_w1200_h678_fmax.jpg)
NEXT YEAR
Lismore Library - January 2023
Lismore City Hall - September 2023
Lismore Regional Gallery - May 2023
Lismore Airport Terminal - June 2023
Lismore Cattle Sale Yards - June 2023
Lismore Memorial Baths - June 2023
CWA Building - May 2023.
![The toilet block in Browns Ck / Clyde Campbell Carpark was destroyed in the February 28 flood. Picture: Cathy Adams The toilet block in Browns Ck / Clyde Campbell Carpark was destroyed in the February 28 flood. Picture: Cathy Adams](/images/transform/v1/crop/frm/154120782/4f76612b-ffb8-4358-a737-a4b902fda79c.JPG/r0_422_8256_5082_w1200_h678_fmax.jpg)
More in 2023:
Also expected to reopen in 2023 are; Albert Park Baseball - clubhouse and amenities (parks open November 2022; Caniaba St Reserve - soccer clubhouse; Clyde Campbell Carpark toilet; ELGAS; Laurie Allen Centre; Lismore Basketball Association; Lismore Lake buildings; Lismore Park Elaine Blanche Tennis Courts; Lismore Preschool; Marie Mackney Netball clubhouse; Municipal Building, Old Council Chambers; Old Helicopter building; Riverview Park clubhouse and canteen.
![Lismore Memorial Baths will reopen next year. Lismore Memorial Baths will reopen next year.](/images/transform/v1/crop/frm/154120782/05d9bedb-efe0-4fe9-b91e-d6973a394fa6.jpg/r105_0_856_422_w1200_h678_fmax.jpg)
In 2022:
Assets due to open by the end of 2022 are: ACE Community Colleges; Albert Park Baseball - canopy, storage & parks; Arthur Park Archery Club; Arthur Park toilet block; Gundurimba Building; Cedar Log shed; Croquet Club; Dawson Street toilet; Dungarubba Reserve toilet block and shelter; Lismore Lake buildings; Lismore Pipe Band building; Lismore SES Headquarters; Lismore Transit Centre; Magellan Street toilet; McKenzie Park toilet block/kiosk; Mortimer Oval new & old building; Nesbitt Park; Radio Controlled Car building; Rhodes Street Park; Richards Oval - Workers Soccer clubhouse; Riverside Park; Riverside Park toilets; Riverview Park; Riverview Park toilets; Sam Trimble Oval amenities, Bexhill; Visitor Information Centre; Visitor Information Centre toilets; W Tresise Railway Park; Wade Park toilet block; Wyrallah Park amenities.